Project Profile
Morris Center

15/11/2022

The Morris Center

The Morris Center is a four-story, 40,000 square-foot mixed use building containing office, research, and retail space. It also houses the shared-energy EcoDistrict which powers the Catalyst Building (and the future South Landing campus), through an all-electric central energy plant and thermal and electrical storage. Thousands of IoT sensors backed by machine learning algorithms pull Avista beyond the meter, provided the visibility needed to balance on-site energy generation and demand with overarching grid operations.

Value Proposition / Benefits

Enabling Efficiencies through Standardization

Asset Standardization

Given the complexity of new product development, Overcast worked closely with MEFPT engineers to realign equipment layouts to create an efficient integrated ceiling system. In parallel, Overcast Engineering developed product families to maximize engineering reuse (+85%) and accommodate the various space and use case types. The standardization of product families enabled engineering, manufacturing, and field installation efficiencies and quality advances via common systems/device interfaces and well documented assembly and install instructions.

Schedule & Labor Efficiencies

This project leveraged a singular crew for device installation as opposed to utilizing the traditional approach, which would require a separate crew for all five trades in the ceiling space. This provided significant productivity increases and schedule savings. Additional schedule savings were achieved by downstream trades associated with the installation of the Cloud routes. This installation consolidation meant that 16 Clouds were installed each day which is the equivalent of ~80 devices were installed per day, leading to ~18 days saved on the schedule.

TRADITIONAL Approach & Cost Utilizing Overcast Cloud & Spline Solution
scope of work items quantity $/sf total quantity $/sf total delta
general contractor scope
Cloud panel installation 120 $30,720 $30,720
Acoustic ceiling panel costs 18,200 8.50 $154,700 3.60 ($154,700)
mechanical scope
HVAC Mechanical systems (Materials & Labor) 18,200 1.65 $30,030 2,400 0.00 ($30,030)
Fire Suppression/Fire Sprinkler 18,200 4.54 $82,628 18,200 3.35 $60,790 ($21,658)
electrical scope
Lighting Fixtures (Materials & Labor) 18,200 22.35 $406,770 18,200 6.12 $111.384 ($295,386)
Low Voltage Pathway wiring 18,200 3.24 $58,968 18,200 2.09 $38,038 ($20,930)
Fire Alarm horns & strobes (Materials & Labor) 18,200 6.05 $110,110 18,200 4.79 $87,178 ($22,932)
Audio-Visual (Materials & Labor) 18,200 7.15 $130,130 18,200 5.11 $93,022 ($37,128)
IT (WAP) (Materials & Labor) 18,200 5.15 $93,730 18,200 3.72 $67,704 ($26,026)
other related scope of work items
Design and Field Coordination TBD
Subcontractor Startup & Commissioning TBD
Jobsite Equipment Staging & Logistics TBD
overcast cloud & spline scope items
Cloud Appliances 120 $421,510 ($421,510)
Total cost $1,163,344 $1,006,784 ($156,650)
total cost savings/sf $8.60
In-Direct Project Cost Savings
General conditions 8% ($12,525)
Bonds and Insurance 2% ($3,131)
Contractor's Fee 4% ($6,262)
Design Contingency 5% ($7,828)
Construction Contingency 3% ($4,697)
SUB-TOTAL ($34,443)
project total direct & indirect cost savings ($191,003)
total cost savings / SF Total $10.49